Republic Transmission, which is owned by LSP Power and Hoosier Energy Rural Electric Cooperative, filed a formula rate at FERC in ER 19-605. Republic Transmission was selected in a MISO competitive process to build a new 345 kV transmission line providing market efficiency benefits, to be constructed between the existing Duff substation in Indiana and the existing Coleman substation in Kentucky (the “Project”). The Project has an expected in-service date of June 2020.
The formula rate has some innovative approaches in order to incorporate the results of the competitive process. The formula rate includes: