FERC is issuing two orders today dealing with transmission reforms. Here is summary of the two orders:
Order 1920 The grid rule contains these major elements:
More specifically, the rule requires each transmission operator to:
The grid rule contains these cost-allocation provisions:
The grid rule requires transmission providers to:
Order 1977 With respect to the Commission’s siting authority, the Infrastructure Investment and Jobs Act of 2021 (or “the IIJA”) clarified that the Commission may issue an interstate transmission project permit if a State has denied an application. In that process, the Commission must determine, as a precondition to a permit holder exercising eminent domain authority, that the permit holder has made “good faith efforts to engage with landowners and other stakeholders early in the applicable permitting process.” First, rule clarifies that the Commission has the authority to issue permits to construct or modify electric transmission facilities in a National Corridor if a State has denied a siting application. Second, the draft final rule codifies the Applicant Code of Conduct. Compliance with the code of conduct is one way that an applicant may demonstrate that it has made good faith efforts to engage with landowners early in the applicable permitting process. The Applicant Code of Conduct includes recordkeeping and information-sharing requirements for engagement with affected landowners, as well as general prohibitions against misconduct. Third, the rule requires applicants to develop engagement plans that describe completed and planned outreach to environmental justice communities and Indian Tribes. A Tribal Engagement Plan was added to the rule in response to comments. Applicants will provide this information as part of a Project Participation Plan, which must be filed early in the pre-filing process. The rule updates and clarifies the environmental information required for existing applicant-prepared resource reports - three new resource reports in which applicants must provide information regarding a proposed project’s impacts on air quality and environmental noise, on environmental justice communities, and on Tribal resources. As part of the new Air quality and environmental noise resource report, and consistent with the Commission’s obligations under NEPA and the Clean Air Act, the applicant must estimate emissions and noise from the proposed project and the corresponding impacts on air quality and the environment. The report must also describe any proposed mitigation measures. In addition, the rule establishes an operational noise limit for proposed substations and related facilities at nearby noise-sensitive areas, such as schools, hospitals, or residences. In the new Environmental justice resource report, the applicant must begin by using current guidance and data to identify environmental justice communities within the area of potential project impact. Once environmental justice communities have been identified, the applicant must describe the impacts of project construction, operation, and maintenance on those communities. In addition, the resource report must discuss cumulative impacts, describe any proposed mitigation measures, and describe any community input received on the proposed mitigation measures. If adopted by the Commission, the final rule will become effective 60 days after publication in the Federal Register.
0 Comments
Leave a Reply. |
Dr. Paul DumaisCEO of Dumais Consulting with expertise in FERC regulatory matters, including transmission formula rates, reactive power and more. Archives
May 2024
Categories
All
|